EP 1110-1-30
3130 Aug 01 Nov 00
forms and facility floor plans, sketches and drawings provided with this SOW shall be recorded
in field notes submitted as an attachment to the Survey Report.
2.2.1
Visual Examination
a. Lead: The Contractor shall conduct a visual examination of both vertical and horizontal
interior and exterior surfaces/component systems to be impacted by the work for determining the
presence of lead. Examples of potential lead-containing surfaces/component systems are listed
in Table B-2.
b. Asbestos: At the same time the Contractor is identifying potential sources of Lead-Based
Paint to be impacted by the work that requires sampling, the Contractor shall conduct a thorough
visual examination of interior and exterior areas for the purpose of determining the presence of
ACM. The Contractor shall identify all potential ACM that will be impacted by the project.
Potential asbestos-containing materials found in buildings are listed in Table B-3. The
Contractor shall determine the friability of all suspected ACM as classified by NESHAP, i.e.
Friable, Non- friable Category I or Non- friable Category II. Each homogeneous area shall be
identified and noted as such in the field notes for selecting sample locations.
2.2.2
Samp le Location Selection
******************************************************************************
NOTE: In certain situations, it is acceptable to allow the Contractor to use
previously collected asbestos survey data for the determination that a
homoge neous area is asbestos-containing rather than collecting and analyzing
new bulk samples. Coordinate with the customer (installation POC) and
determine if previous installation asbestos survey data for the building(s) areas to
be included in the project design should be provided to the Contractor. If it is
determined that pre-existing data is valid, then it shall be attached to this SOW
and the bracketed paragraph selected. The Contractor will be required to review
and accept the data prior to considering it in selecting sample locations, or provide
justification why such data cannot be used. Coordinate with the customer
(Installation POC) for scheduling the survey sampling including destructive
sampling during occupied and/or non-occupied hours.
******************************************************************************
The Contractor shall select sample locations for the lead containing painted surfaces [and soil]
and ACM during the visual assessment. [Prior to selecting the ACM sample locations, the
Contractor shall review per-existing asbestos survey data provided as an attachment to this SOW
and take the data into consideration in selecting the sample locations. If the Contractor
determines that some or all of the pre-asbestos survey data provided is not acceptable for
consideration in the survey, the Contractor shall state in writing to the Contracting Officer the
reasons why the data cannot be used. The CO shall make the final decision regarding the
usability of any pre-existing data provided to and rejected by the Contractor. The final decision
by the Contracting Officer on rejected pre-existing data will be given to the Contractor prior to
the Contractor's sample location selection.] Each location shall be described in field notes or
indicated on the facility [CADD] floor plans, sketches and drawings and by filling in the
A-11