EP 1110-1-30
3130 Aug 01 Nov 00
NOTE: Consult with the customer to determine schedule milestones. Combine
meeting topics where appropriate. At a minimum, the schedule milestones are:
1)
Site visit/project walkover
2)
Project Work Plan submission/Start-up meeting
3)
Data certification/progress report submission
4)
Final Survey Report submission
******************************************************************************
[Insert appropriate schedule milestones]
3.7
SUBMITTALS
3.7.1
Project Work Plan
3.7.2
Survey Progress Reports
[The Contractor shall provide [ ] project progress reports to the COR. The reports shall be due
to the COR [ ] The reports shall address [ ]]
3.7.3
Survey Data Submission in Electronic [HALO] [ ] Format
The Contractor shall provide a survey data submission in electronic [HALO] [ ] format, as
described in Paragraph 2.4 above.
3.7.4
Survey Report
The Contractor shall provide a survey report, as described in Paragraph 2.4 above.
3.8
MISCELLANEOUS
3.8.1
Glossary
This paragraph contains a glossary of terms used in this SOW, or commonly used in reference to
lead and asbestos surveys.
Asbestos
The asbestiform varieties of: Chrysotile (serpentine); crocidolite (riebeckite); amosite,
anthophyllit e; tremolite; and actinolite. (40 CFR 763.83)
Asbestos -containing
Any material or product which contains more than 1 percent asbestos. Including
material (ACM)
surfacing ACM, thermal system insulation ACM, or miscellaneous ACM that is found
in or on int erior structural members or other parts. (40 CFR 763.83)
Asbestos debris
Pieces of ACM that can be identified by color, texture, or composition, or means dust,
if the dust is determined by an accredited inspector to be ACM. (40 CFR 763.83)
Asbestos -cont aining waste
Mill tailings or any waste that contains commercial asbestos and is generated by a
materials
source subject to the provisions of this subpart. This term includes filters from control
devices, friable asbestos waste material, and bags or other similar packaging
contaminated with commercial asbestos. As applied to demolition and renovation
operations, this term also includes regulated asbestos-containing material waste and
materials contaminated with asbestos including disposable equipment and clothing.
A-27