EP 1110-1-29
31 Aug 01
******************************************************************************
NOTE: Some states or local jurisdictions may use different terminology for individuals
certified to complete the services described in this SOW, i.e., the certificate may include
a title other than "risk assessor."
******************************************************************************
The Contractor shall employ a certified risk assessor to complete the assessment described in this
SOW.
3.1.2.1
EPA Certification
EPA certification (or certification under an EPA-approved state program) is required pursuant to 40
CFR 745.226 (64 FR 42849, 6 August 1999).
3.1.2.2
State and Local Certification
Each risk assessor shall possess current certification or licensing required under state or local
jurisdictions, if applicable, in addition to or in place of EPA certification, depending on the requirements
of the jurisdictions.
3.1.2.3
Evidence of Certification
A copy of each current applicable certificate shall be included in the Project Work Plan for each
Contractor risk assessor participating in this project.
3.1.2.4
Record of Experience
A resume or other description of the certified risk assessor's experience, which is directly applicable to
the activities required under this SOW shall be included in the Project Work Plan.
3.1.2.5
Clearance Teams
******************************************************************************
NOTE: Indicate the number and size of clearance teams for large, complex projects.
******************************************************************************
The Contractor shall specify in the Project Work Plan the number of risk assessors and clearance teams
that are to be used to perform the clearance inspection(s) addressed in this SOW. No more than [insert
appropriate number] risk assessors per team shall be assigned to conduct the clearance inspection(s).
Team leaders shall have a minimum of three years experience in conducting lead clearance activities
3.1.2.4
Project Manager Experience
[The project manager shall have a minimum of three years experience in managing lead clearance
inspections.] A resume or other description of the project manager's experience that is directly
A-27