EP 1110-1-29
31 Aug 01
Address and age of each building [unit].
Unit number
The date of [each] clearance..
Verification of lead hazard controls implemented in accordance with original project
SOW, based on a visual examination for each unit subject to a clearance inspection.
Clearance Sampling Plan with post-sampling documentation
The Laboratory Report
The Contractor's certification that the NLLAP required QA/QC data generated by the
laboratory are valid and meet the SOW requirements for each of the sample batches
analyzed.
2.4.2
Contractor Data Certification
The Contractor shall certify that the data used to develop the conclusions of the clearance have been
reviewed and validated, and have met the DQOs defined in Paragraph 1.3.3.
2.4.3
Electronic [HALO/] Installation Data Downloading into Installation System
************************************************************************
NOTE: All data collected during activities specified in this SOW is to be provided to
the Army in a format compatible with the Army's Hazardous Asbestos and Lead
Optimal Management System (HALO) or, if the installation does not utilize HALO,
compatible with the installation data management system requirements. HALO is a
hazard management system designed to track lead and asbestos hazards and actions
taken in response to identified hazards. HALO requires an IBM-compatible personal
computer (with a Pentium processor), Windows 95, 16 MB of RAM, 10MB of
available hard disk space, Word 97, and display resolution of 800x600 pixels. The
current point-of-contact (POC) for HALO is:
USACE Engineering Research and Development Center (CEERDC)
(217) 352-6511, ext. 7239 (commercial)
Where the installation has no unique data management system for LBP data, HALO will
be the default program for all deliverables under this SOW. The SOW should detail the
procedure for the Contractor to follow in providing the results of the lead clearance
inspection to the Contracting Officer for uploading into HALO or other system used by
the installation.
At a minimum, the Contractor must be provided with a copy of the HALO Data
Dictionary. The dictionary identifies the table names, field names, data types, and any
A-25