are likely to be used. It may be cost-effective to overnight mail samples to remote labs
with known proficiency and cost savings in lead analysis. This information can easily be
obtained by asking some of the large national consultants that do business with the
District Office in other areas. In the bid, ask the contractor to provide a unit cost per
sample to be charged by them in calculating their overall proposal, in the event additional
samples beyond those projected must be collected once the contract begins (e.g., re-
sampling certain areas, etc.) or there is a reduction in samples. Consult with the
contracting officer. Also include the requirement for a preliminary site walkover.
******************************************************************************
Bid assumptions include: [insert assumptions as applicable]
2.0
PROJECT REQUIREMENTS
2.1
TASK 1 DESCRIPTION OF CURRENT CONDITIONS/PROJECT WORK PLAN
******************************************************************************
NOTE: Determine the need for the Contractor to review informatio n contained in the
installation's Lead Hazard Management Plan if one is available and conduct interviews
with personnel familiar with the unit histories, in the Contractor's development of the
Project Work Plan and Risk Assessment Sampling Plan.
******************************************************************************
2.1.1
Background Data
The Contractor shall review general information on physical characteristics and occupant use
patterns affecting children under six years old for the units that will be addressed in the lead
inspection/risk assessment, [and preexisting survey data ] prior to performing Task 2.
2.1.1.1
Lead Hazard Management Plan Review
[The Contractor shall review the installation's Lead Hazard Management Plan, including the
history of LBP hazards in the units to be assessed in this SOW.]
2.1.1.2
Interviews
[The Contractor shall conduct interviews of personnel familiar with facility history and with
facility use patterns. Personnel to be interviewed shall include:
a. Installation Lead Hazard Management Team Leader
b. Installation Environmental Officer - to determine if LBP has been found in
previous assessments, to identify LBP locations, to verify maintenance histories, and to
A-12