information including installation or building designations, unit addresses and floor plans.
Attach the information to the SOW. Summarize any physical characteristics and
occupant use pattern information (see Glossary) that may be relevant to the risk
assessment in light of the property transfer, that the Contractor must review by 40 CFR
745 Subpart L. This SOW requires the Contractor to collect detailed physical
characteristics information during the visual asse ssment in Task # 2 using Forms 1 and 2
(Figure B-1 and Figure B-2, Appendix B).
******************************************************************************
The Contractor shall perform lead inspections/lead risk assessments at [insert unit description
information]. Procedures and requirements for conducting these activities are defined in the
following paragraphs. The physical characteristics, and occupant use patterns include [insert
physical characteristic and occupant use pattern descriptive info rmation].
1.3.2
Previous Studies and Results
******************************************************************************
NOTE: Include previous lead studies and results that are to be reviewed and considered
by the lead inspector/risk assessor in making decisions and conclusions for the work
specified in this SOW.
******************************************************************************
[Prior to initiating field activities required by this SOW, the lead inspector/risk assessor shall
review the previous study data results collected at the location(s) provided as an attachment to
this SOW.]
1.3.3
Project Work Tasks/Description or Work
The project work tasks include: [describe each project specific work task that is required to
accomplish the Tasks described in this SOW]. The lead inspections/risk assessments shall
include a visual assessment, and sampling each testing combination (see Glossary) for the
presence of LBP, and where found, sampling for the identification of lead hazards at each unit
included in the survey. Procedures and requirements for completing the inspection/risk
assessment activities are defined in the paragraphs that follow. The combined lead
inspection/risk assessment shall be performed at one time in each selected unit.
1.3.4
Unit Selection Strategy
******************************************************************************
NOTE: All lead inspections/risk assessments involving multi- family housing units
greater than 20 units of similar construction and maintenance histories at Army
installations shall be evaluated using random sampling strategy. All single unit housing,
multi- unit housing comprised of 20 or fewer units, and all units that have dissimilar