EP 1110-1-22
15 Sep 00
1.2
REGULATORY REQUIREMENTS
1.2.1
Regulatory Authority/Requirements
The Contractor shall conduct all work in accordance with Federal, state and local regulations and
requirements. Where inconsistencies exist between Federal, state, and local requirements and this
SOW, the Contractor shall follow the most protective requirements.
1.2.1.1 Federal Requirements
a. Survey and Assessment Procedures and Requirements
Following the AR 200-1 and AR 420-70, all persons conducting asbestos surveys and/or
assessments shall possess current USEPA asbestos training certifications as specified in 40 CFR
Part 763, Sub-part E, Appendix C. The types of certifications required for specific tasks are
detailed in this SOW. The Contractor shall complete the asbestos surveys and assessments
utilizing the guidance provided in PWTB 420-70-8, Installation Asbestos Management Program,
Chapter 5 (Appendix B), Chapter 8 and in Asbestos Hazard Emergency Response Act (AHERA)
protocols.
b. Health and Safety Requirements
*******************************************************************************
NOTE: The procedures discussed in 29 CFR 1910.146 must be considered when a
potential for confined space entry (i.e., crawl spaces, duct work, vaults, etc., which
meet the definition of a confined space) exists.
*******************************************************************************
The Contractor shall comply with OSHA requirements, particularly 29 CFR 1910.134 and 29 CFR
1910.1001, during the performance of activities described in this SOW. Special emphasis shall be
placed on safe practices for confined space entry, fall protection, and electrical hazards. The
Contractor shall also follow all requirements stated in the USACE Safety and Health Requirements
Manual (EM 385-1-1), including submission of an Accident Prevention Plan (APP). Field
activities shall not be initiated before the Contracting Officer's designated Contracting Officer
Technical Representative (COTR) has accepted the APP.
1.2.1.2 State and Local Requirements
*******************************************************************************
NOTE: Reference state, local, (OCONUS where applicable) or installation specific
requirements that differ from the Federal requirements cited above that are
applicable to the work addressed in this SOW.
*******************************************************************************
[The Contractor shall comply with the following state [and local] [ and installation] requirements
A-5