Geophysical Plan.
Site Safety and Health Plan.
Location Surveys and Mapping Plan.
Work, Data, and Cost Management Plan.
Property Management Plan.
Sampling and Analysis Plan.
Quality Control Plan.
Environmental Protection Plan.
Investigative Derived Waste Plan.
(b) The Work Plan will be prepared in accordance with contract requirements. Additional
information on Work Plan requirements is provided in the OE MCX DID OE-005-01, "Work
Plan", which is located on the OE MCX website at http://www.hnd.usace.army.mil/oew.
(2) Review and Approval.
(a) The OE Design Center is responsible for executing the Work Plan. The district will
review the Work Plan and provide comments or written concurrence or non-concurrence. The
OE MCX will monitor the Work Plan.
(b) When review of the draft document is completed, the government will provide
comments to the contractor for incorporation into the final document. A minimum turnaround is
expected, and the final document will be back-checked for adequate revisions. Once the draft
comments are incorporated, the document may be sent to regulators or other stakeholders for
review and comment. The OE Design Center will approve the Work Plan.
(3) Changes to the Work Plan.
(a) Changes are often required to the Work Plan during execution of removal projects. The
OE Design Center and CO will approve any changes to the Work Plan in coordination with the
PM. The approved changes should be made to the Work Plan within 21 days.
(b) A Work Plan change that affects any operational and/or safety procedures may also
require a revision to and a re-submittal of the ESS. The OE MCX must approve any changes to
the ESS.
11-5