EP 1110-1-18
24 Apr 00
(2) An example removal action SOW is located on the OE MCX website at
http://www.hnd.usace.army.mil/oew. The following tasks are typically included in the SOW:
(a) Site visit.
(b) Work Plan preparation.
(c) Location surveying and mapping.
(d) Site preparation.
(e) Geophysical investigation.
(f) OE removal.
(g) Institutional analysis.
(h) Quality control.
(i) Public affairs assistance.
(j) Final Report.
(3) The OE MCX may be consulted to provide the appropriate statements or paragraphs
concerning background and authority for the task order's award.
(4) The SOW will be reviewed by the PM, OE Design Center personnel and other
appropriate personnel, as required.
b. Preparation of the IGE. The IGE for an OE removal action will be prepared in
accordance with the guidance provided in Chapter 3.
c. Removal Action Contract Award. Following the approval of the SOW and IGE, the
removal action contract is solicited and awarded.
11-3. Site Visit.
a. The site visit is conducted to provide the UXO contractor with the opportunity to gather
pertinent information for use in preparing the cost estimate and project planning documents.
b. Site Visit Task Order/Purchase Order. The site visit may be awarded as a task in the
removal action task order or as a stand-alone task order/purchase order. Sample SOWs for
awarding the site visit as either a task in the overall removal action task order or as a stand alone
task/purchase order are located on the OE MCX website at http://www.hnd.usace.army.mil/oew.
11-3