WBS Number
DESCRIPTION
QTY
UOM
UNIT
COST
COST
$
34XXX
HTRW POST CONSTRUCTION AND FINANCIAL
CLOSEOUT ACTIVITIES
FISCAL/FINANCIAL CLOSE ACTIVITIES
341XX
342XX
HTRW OPERATION AND MAINTENANCE (POST
CONSTRUCTION)
02
MONITORING, SAMPLING, TESTING, AND
EA
02
01
Meteorological Monitoring
EA
02
02
EA
02
03
Air Monitoring and Sampling
EA
02
04
Monitoring Wells
EA
02
05
EA
02
06
Sampling Soil and Sediment
EA
02
07
Sampling Asbestos
EA
02
08
Sampling Radioactive Contaminated Media
EA
02
09
Laboratory Chemical Analysis
EA
02
10
Radioactive Waste Analysis
EA
02
11
Geotechnical Testing
EA
02
12
02
13
On-site Laboratory Facilities
EA
02
14
Off-site Laboratory Facilities
EA
02
9X
Other (Use Numbers 90-99)
EA
SITEWORK
03
SY/YR
03
04
Roads/Parking/Curbs/Walks
LF/YR
03
05
Fencing
LF/YR
03
06
Electrical Distribution
LF/YR
03
07
Telephone/Communication Distribution
LF/YR
03
08
Water/Sewer/Gas Distribution
LF/YR
03
09
Steam and Condensate Distribution
LF/YR
03
10
Fuel Line Distribution
LF/YR
03
11
SF/YR
03
12
Permanent Cover Structure Over Contaminated Area
EA/YR
03
14
Fuel Storage Tanks (New)
03
9X
Other (Use Numbers 90-99)
05
SURFACE WATER COLLECTION AND CONTROL
LF/YR
05
01
Berms/Dikes
Floodwalls
SF/YR
05
02
LF/YR
05
03
Levees
LF/YR
05
04
Terraces and Benches
LF/YR
05
05
Channels/Waterways (Soil/Rock)
LF/YR
05
06
Chutes or Flumes
LF/YR
05
07
Sediment Barriers
LF/YR
05
08
ACR/YR
05
09
Lagoons/Basins/Tanks/Dikes/Pump System
MGA
05
10
Pumping/Draining/Collection