SECTION SEVEN
Operations and Maintenance Activities
Operation Phase Performance
Parameter
Goal
Achieved
Utilization %
86.0%
75.0%
Utilization Avg. TPH
40.4 TPH
35.3 TPH
Availability %
71.0%
78.1%
Availability Avg. Daily Tons
688.8 Tons
660.7
Availability TPH
28.7 TPH
27.53 TPH
Ash Req. Add. Thermal Treat
5%
2.7%
The Operation Phase was complete on April 22nd, 1999 when the final soil to be incinerated was
fed to the TDF. Final bottom ash analytical results were received on April 23, at which time the
TDF burners were shut off and the Demobilization Phase started.
7-2
Slippery Chemical OU 3 Final RA Report