EP 1110-1-18
24 Apr 00
and investigation occur. The dig sheet capture minimum data to allow the OE project team and
stakeholders to easily understand what was found at the site.
c. Additional information on Site-Specific Removal Report requirements can be found in
the OE MCX DID OE-030, which is available on the OE MCX website at
http://www.hnd.usace.army. mil/oew.
13-3. Submittal.
a. The contractor will be required to submit the draft Site-Specific Removal Report in
accordance with the SOW. Normally, the SOW requires the report to be submitted in draft form
within 21 days of the completion of all field work.
b. The Site-Specific Removal Report should be submitted in digital format, including all
text, drawings, maps, forms, tables, field notes, and other data gathered during the removal
action. The format requirements should be coordinated among OE project team members at the
time the contract or task order is prepared. Specifications for the digital format should be
developed with the objectives of user compatibility and posting the report on the Internet.
13-4. Review and Approval.
a. The Site-Specific Removal Report is reviewed by the district and the OE MCX. It is
critical that the USACE review this report for completeness, accuracy, and compliance with the
contract/task order terms. The contractor will make all necessary corrections as directed by the
CO prior to publishing the report as a final document.
b. The OE Design Center will provide approval of the Site-Specific Removal Report. A
copy of the final report will be placed on file in the Administrative Record.
13-2