12-8. OE Scrap Disposal. The fragments and components from the on-site or in-place
destruction of OE items will be gathered, inspected, and turned-in as OE scrap. Contact the OE
MCX for additional information on the disposal of OE scrap.
12-9. Demobilization.
a. Demobilization may occur for a variety of reasons, including:
(1) The project may be completed with all work accomplished.
(2) The project may be incomplete, but the contractor has expended most of the contract
funds.
(3) Adverse weather conditions.
(4) Determination that continuing in the present course of action is not in the best interest
of the government.
b. A demobilization plan will be developed, as a part of the Work Plan, by the contractor
in close coordination with the PM, OE Design Center, OE Safety Specialists, and the customer.
Authorization to demobilize from a site must be issued in writing to the contractor from the CO.