activities required to demonstrate that Federal participation in a
project is warranted, and completes all activities to award the
construction contract. The PDA begins with issuance of funds for
initial analysis and ends (within a 12 month target time) with the
division request for construction funds. HQUSACE role during the
implementation process is limited to assessing the financial impact of
funding requests on the Section 14 program, and the routine
acknowledgement of construction funding commitment. HQUSACE monitors
policy compliance and technical adequacy by way of audits at periodic
program review meetings (i.e., there is no HQUSACE policy or technical
review or approval during the implementation process). (ER 1105-2-
100)
15-6. Technical and Engineering Assistance on Streambank Erosion.
Section 55 of Public Law 93-251 authorizes the Secretary of the Army,
acting through the Chief of Engineers, to provide technical and
structural and non-structural methods of preventing damages
attributable to shore and streambank erosion.
15-7. Streambank Erosion Resulting from Project Construction and
Operation. See paragraph 11-8.
15-3