EP 1165-2-1
30 Jul 99
Table 12-1, Non-Federal Share, Studies, PED
Preconstruction
Commercial
Recreational
Inland
Work
Navigation
Navigation
Waterways
-0-
-0-
-0-
Feasibility Study
50%
50%
-0-
PED
--------(See Construction)---------
c. Construction, Operation, and Maintenance. Sections 101,
102, and 103 of WRDA 1986, as amended, specify the cost sharing for
commercial harbor, inland waterway, and recreational navigation
projects, respectively.
(1) Harbors. Section 101, as amended, requires the project
sponsor to bear a percentage share of harbor construction costs for
project components that are cost-shared (general navigation features,
mitigation), that varies according to the range of water depths where
the work is done (20 feet or less, greater than 20 feet but not in
excess of 45 feet, and greater than 45 feet). This variable cost
share is paid during construction. In addition, Section 101 requires
the sponsor to pay 10 percent of the construction costs that are
cost-shared, on completion of construction or over time with interest,
up to 30 years. Credit against this 10 percent contribution is
allowed for the value of lands, easements, rights-of-way, relocations,
and the non-Federal sponsor share of deep-draft utility relocations.
(2) Waterways. Waterways that are determined to be "inland
waterways" for the purpose of Section 102 are exempt from cost
sharing, and construction and O&M are 100 percent Federal. Waterways
that are not "inland waterways" are cost shared as commercial or
recreational harbors depending on project purpose.
(3) Recreation. Section 103 sets fixed percentages for the
non- Federal share of construction and O&M costs for recreation
projects (50 and 100 percent, respectively). These cost shares apply
to recreational navigation projects, and the joint and separable costs
allocated to recreation in other navigation projects.
Table 12-2, Non-Federal Share, Construction, Operation and Maintenance
Commercial Navigation
(Cost Assignable to Project Depth:) Recreatn
Inland
to 20'
>20' to 45'
>45'
Navigatn
Waterways
(to 6.10
(>6.10m to (>13.72m)
meters(m))
13.72m)
Construction
GNF, incl Mit.
10%+10%1/
25%+10%1/
50%+10%1/
50%
-0-
Aids to Navigation -0-
-0-
-0-
-0-
-0-
LSF
100%
100%
100%
100%
-0-
LERR
100%
100%
100%
100%
-0-
Operation and
Maintenance
GNF, incl Mit.
-0-
-0-
50%
100%
-0-
Aids to Navigation
-0-
-0-
-0-
-0-
-0-
LSF
100%
100%
100%
100%
100%
1/ This additional 10% of GNF may be offset by creditable LERR.
12-6.
Navigation Project for General Versus Restricted Interest.
12-6