EP 1165-2-1
30 Jul 99
(1) All further preconstruction engineering and design work
will be cost shared in the same percentages as specified in Public Law
99-662 for the project purposes.
(2) Construction costs will be shared in the same percentages
as specified in WRDA 1986, as amended, for the project purposes.
c. Provision of the non-Federal share of preconstruction
engineering and design costs may be deferred until the first year of
corrective measures construction. The non-Federal share of the
construction costs will be provided, in each year of construction,
proportionate to the anticipated Federal expenditures in that year.
6-16