EP 1165-2-1
30 Jul 99
(c) expanding any confined dredged material disposal facility
authorized by Section 123 of the River and Harbor Act of 1970, for
which the capacity of the confined dredged material disposal facility
was exceeded in less than six years.
(5) Dredged Material Disposal Facility Partnerships (Section
217 of WRDA 1996).
(a) The SA/Federal Government may, at the request of a non-
Federal interest, add capacity at a dredged material disposal site
being constructed by the SA/Federal Government if the non-Federal
sponsor pays, during the period of construction, all costs associated
with the additional capacity. The non-Federal interest can set and
collect fees assessed to third parties to recover those costs.
(b) The SA/Federal Government may allow non-Federal interests
to use capacity in an existing Corps disposal site if such use will
not reduce the availability of the facility for the Federal project.
The (SA)/Federal Government can impose fees to recover capital,
operation, and maintenance costs associated with the partner's use.
(c) The SA/Federal Government may use public-private
partnerships in the design, construction, management, or operation of
dredged material disposal facilities in connection with construction
or maintenance of Federal navigation projects. These partnerships may
be implemented through agreements with non-Federal interests, a
private entity, or both. Funds for the work may be provided in whole
or in part by the private entity. The SA/Federal Government may
reimburse the private entity, subject to appropriations, for the
disposal of dredged material in the facility through the payment of a
disposal user fee. The fee shall be sufficient to recover the funds
contributed by the private entity plus a reasonable rate of return on
investment. The Federal share of the fee shall equal the Federal
percentage of the disposal facility cost, in accordance with existing
cost sharing requirements.
(6)
Cost Sharing Applications.
(a) Where channel deepening is not limited to one depth zone
(e.g., where a channel is being deepened from 40 to 50 feet) cost
sharing is determined as shown in Appendix G to ER 1165-2-131. This
approach also applies to GNF features associated with such a project
which involves deepening which crosses different depth zones such as
widenings, turning basins, and anchorage areas. The existing and
improved main channel depths will be used to determine cost sharing
(e.g., for a channel deepened from 40 to 50 feet, there are two depth
zones - one to from 40 to 45 feet, and a second from 45 to 50 feet -
even though widening or other GNF features may be in areas that have
natural depths of 20 feet or less).
(b) Where channel deepening is limited to one depth zone (e.g.,
where a channel is deepened from 40 to 45 feet) cost sharing is
determined by the improved depth.
(c) Where channel deepening is limited to one depth zone (e.g.,
where a channel is deepened from 40 to 45 feet) the cost sharing for
the entire cost of GNF associated with that deepening project are
determined by the improved depth (e.g., if there is channel widening
associated with a project deepened from 40 to 45 feet, all of the
widening costs will be shared at the cost sharing which applies to the
45 foot depth (25 percent during construction) even though the
6-5