(3) Issues From Regional Team Members. Each Team member will be
responsible for obtaining input from their division office, district offices, project offices,
and recreation stakeholders (as appropriate). Team members will present both policy
issues as well as RMSP proposals for management studies, management assistance, and
information exchange.
(4) Status of Ongoing RMSP Activities. HQUSACE, ERDC, or others
responsible for ongoing RMSP activities will provide a status report on each RMSP
funded activity.
(5) Status of Overall RMSP Program. The HQUSACE and ERDC Team
members will provide an overview of the total RMSP program funding status for the
previous and upcoming fiscal years so that funding adjustments can be considered.
c. The fall Team meeting will result in the following products:
(1) The identification of high priority policy issues to be addressed by
HQUSACE.
(2) The identification of high priority RMSP needs to be further developed for
consideration during the spring Team meeting.
(3) The recommendation of a "Proponent" for each high priority RMSP need who
will be tasked with developing a written "Statement of Need" to better define the
customer's expectations.
(4) The tasking of ERDC to work with each "Proponent" in the development of a
"Proposed Study Plan" for consideration during the spring Team meeting.
(5) Recommendations to HQUSACE for minor adjustments to the current fiscal
year work plan and long range work plan.
15-6. Spring Team Meeting.
a. The primary purpose of the Spring Team Meeting will be to review "Statements
of Need/Proposed Study Plans" and to develop recommendations for new starts for the
upcoming fiscal year. The following input will be available to the Team during the spring
meeting: