EP 1130-2-500
27 Dec 96
i. Boom discharge - Type and dimensions (Where applicable)
I-6. MACHINERY
a. Propulsion
(1)
(2)
Number, size and type of engines, generators and/or motors
(3)
(4)
Controls
(5)
Instruments
b. Dredging
(1)
Pump (Number, size, capacity, dynamic head, etc.)
(2)
Pump motors (number, size, characteristic)
(3)
Gas ejection system
(4)
Instruments
c. Miscellaneous
(1)
Auxiliary power
(2)
(3)
Piping
(4)
Electronic Equipment (Radio, Radar, Depthfinder, Electronic Positioning, etc.)
I-7. CONSTRUCTION COST ESTIMATE
I-8. SCHEDULES FOR DESIGN AND CONSTRUCTION (including summary of fund
requirements)
I-9. ESTIMATED PRODUCTION (DREDGING)
I-10. ESTIMATED OPERATING COST
a. Estimated plant rental computation
b. Estimated monthly operating cost
(1)
Payrolls
(2)
Subsistence
(3)
Fuel
(4)
Plant rental
(5)
Other direct costs
(6)
Indirect costs (supervision, inspection and overhead)
(7)
Total
c. Estimated average unit costs
I-3