(5) Barges with Cargo Bins and/or Bulwarks. Barges with a rake at each end of the hull
and cargo bins or bulwarks above the deck shall have designation markings similar to that for flat
deck barged with a rake at each end, except that the markings shall be located near the top of the
cargo bin or bulwarks in lieu of on the hull proper. See Fig. K-6, Table K-3, page K-3, for size
lettering. In addition, the designation in a single line "CORPS OF ENGINEERS, U.S. ARMY"
with size lettering as shown in Fig. K-6, Table K-3, page K-3, shall be located on the forward and
aft transverse ends of the cargo bins and/or bulwarks. In lieu of the single line designation a
double line markings may be used of the forward and after transverse ends of the bins and/or
bulwarks with size lettering and spacing to be as shown on Fig. K-8, Table K-3, page K-3.
(6) Barges with a rake at one end of the hull and with a cargo bin and/or bulwark on the
deck, will have the designation markings as specified for single-rake flat deck barges with a rake
at one end except that the markings shall be located port and starboard near the top of the
longitudinal sides of the bin or bulwark. See Fig. K-6, Table K-3, page K-3. In addition, the
forward and after transverse ends of the bins or bulwarks will have the designation markings as
specified above for the double raked barges with bins or bulwarks.
(7) Crane Barges. The crane with no deckhouse will have number and designation
markings as specified for double or single raked hulls of flat deck barges as applicable. In
addition, the designation shown below and as in Fig. K-7, page K-3, will be centered on both
sides of the crane cab.
NUMBER OF BARGE
CORPS OF ENGINEERS
U.S. ARMY
Crane barges with deckhouses will have number and designation markings as specified under
preceding paragraph for barges with long or short deckhouses as applicable plus the crane
markings indicated above on both sides of the crane.
(8) Fuel Barges. Oil barges will have number and designation markings similar to those
specified for flat deck barges with single or double rakes as applicable.
7-10. Descriptive Data.
a. Whenever items of floating plant, both Revolving Fund and Project owned, of the types
indicated below are constructed or otherwise acquired, data thereon will be compiled on the
applicable ENG Form 33A through E, "Description of Plant", and a copy thereof shall be
transmitted to HQUSACE, Attention: CECW-OD within 30 days after the plant is placed in
service. In the event alterations made to plant require correction of data previously submitted,
copies of revised forms will be transmitted within 30 days after completion of the alterations.
b. Applicable forms for submission of data are as follows:
ENG Form 33A - Seagoing hopper dredges, sidecaster dredges and vessels resulting from
the conversion of hopper dredges.
ENG Form 33B - Hydraulic pipeline dredges and booster barges.
ENG Form 33C - Dipper and bucket dredges, derrickboats, maneuver boats, piledrivers,
graders, drill boats and jet probing barges.
7-14