EP 1110-1-29
31 Aug 01
Soil- Lead Hazard: Bare Soil: Child Play Areas
400 g/g
Soil-Lead Hazard: Remainder of Yard Excluding
1200 g/g
Child Play Areas
1.3.4
Bid Assumptions
******************************************************************************
NOTE: Include project-specific assumptions for the Contractor to use in developing a
cost estimate. Provide site-specific information to assist in developing realistic
assumptions. Review Task # 1, Task # 2 and Task # 3 requirements prior to
developing this paragraph. Use the recommended number of dust wipes based on the
treatment category that applies to the project to calculate the average number of wipes
per unit for bidding purposes, i.e., Category #1: 2 dust wipes per room for each room
up to 4 rooms for each unit plus one sample for each 2000 square feet of common area,
etc. In addition to the field wipes, field blanks must be included based on the total
number of field wipes submitted in the batch in accordance with ASTM E 1728.
Sample analysis cost can range to .00. Check with NLLAP qualified laboratories in
the area. At least one dust spike sample must be submitted to the laboratory for the
first 50 field dust wipes, and at a rate of one per 50 field wipes thereafter.
******************************************************************************
Bid assumptions include: [insert bid parameters]
2.0
PROJECT REQUIREMENTS
2.1
TASK 1 DESCRIPTION OF CONDITIONS/PROJECT WORK PLAN
2.1.1
Project Information Review
The Contractor shall coordinate with the Contracting Officer to obtain information describing current
conditions of the facilities to be included in the lead hazard clearance inspection. The information shall
include the [lead hazard control project Contract (#) attached to this SOW] [the lead hazard control
project Contract specification (#)] [and the lead hazard control Contractor completion report].
2.1.2
Site maps identifying individual units and unit numbers for all units to be inspected for clearance, and
copies of floor plans for each type of unit to be inspected are attached as a part of this SOW. The
Contractor shall use these plans in performing Task # 2 to identify and record clearance sample
A-13