EP 1110-1-29
31 Aug 01
NOTE: The cited 40 CFR regulations and June 1995 HUD Guidelines specify clearance procedures for
target housing/child occupied facilities and are the procedures included in this SOW. The procedures
are to be used for both active target housing and target housing slated for BRAC property transfer.
Paint, Dust, and Soil-Lead Hazard definitions in 40 CFR Part 745 Subpart D Section 65 are used in
defining the cleanup clearance action levels for active housing and residential BRAC property transfers
in this SOW.
******************************************************************************
The Contractor shall evaluate clearance against action levels specified in Table A-1 by meeting the Data
Quality Objectives (See Glossary) (DQO) to comply with 40 CFR 745.227(e)(8), (e)(9), and (h) [and
with 24 CFR 35.1340] using methodologies specified and where not specified, using those found in
Chapter 15, "Guidelines for the Evaluation and Control of Lead- Based Paint Hazards in Housing",
Department of Housing and Urban Development (HUD Guidelines, June 1995, as revised) as
summarized in this SOW.
b. Safety and Health
The Contractor shall comply with applicable OSHA standards and with the USACE Safety and Health
Requirements Manual EM 385-1-1 including submitting an Accident Prevention Plan (APP) to the
Contracting Officer (see Glossary) prior to performing field activities. Field activities shall not begin
without acceptance of the APP by the Contracting Officer.
1.2.1.2
State and Local Requirements
******************************************************************************
NOTE: Reference state, local, or installation specific requirements that differ from the
Federal requirements cited in this SOW that are applicable to the clearance to be
performed.
******************************************************************************
[The Contractor shall comply with the following state and local/installation requirements in completing
the activities required by this SOW. [insert applicable requirements ]]
1.3
SITE CHARACTERISTICS, OBJECTIVES AND DESCRIPTION OF WORK
1.3.1
Site Location/Project Characteristics
******************************************************************************
NOTE: Identify all units and surfaces within each unit that will be included in the
clearance inspection. Provide a description of the work tasks and the extent of work
that was performed by the lead hazard control contractor, including a list of surfaces
that did not receive treatment; by providing access to the original SOW, specifications,
and/or contractor completion report.
******************************************************************************
A-9