EP 1110-1-23
31 Jan 99
A. The Monitoring Contractor will provide all personnel, equipment and resources required to
carry out the tasks associated with this project and will coordinate, when necessary, its activities
with the Abatement Contractor. The Monitoring Contractor will coordinate all on-site activities
with the Abatement Contractor, the COR and other affected parties as directed by the COR and
will perform activities on a schedule compatible with the Abatement Contractor's work schedule.
Personnel air monitoring during asbestos abatement projects is the responsibility of the abatement
contractor and is not a task covered by this contract. Personnel performing work tasks covered by
this contract will be monitored for asbestos exposure by the Monitoring Contractor in accordance
with 29 CFR 1926.1101.
******************************************************************************
NOTE FOR PROJECT SCOPE WRITER: Attach copy of the Abatement Hazard Plan as Annex
A. This contract is to include the approved Asbestos Abatement Plan, the Accident Prevention
Plan and those Detailed Drawings related to the air monitoring requirements.
******************************************************************************
2.0 GENERAL SCOPE OF SERVICES
2.1 Review of asbestos abatement contract documents.
2.2 Prepare and submit an Air Monitoring Plan for approval by the Contracting Officer's
Representative (COR).
2.3 Conduct area asbestos air [baseline sampling prior to abatement],[monitoring during
asbestos abatement for environmental quality control],[and] [sampling for final clearance of
asbestos abatement].
2.4 Prepare and submit a final report of laboratory results and daily air monitoring logs.
2.5 Submit monthly progress reports.
3.0 DETAILED DESCRIPTION OF SERVICES
All tasks will be conducted with the concurrence of the Contracting Officer (CO) or the
COR and performed by a designated qualified industrial hygienist(IH) as defined herein. While
A-2