EP 1180-1-1
1 Aug 01
agency in the United States.
c. In the event, the prospective contractor's facility is not found within the Registry, the
Contracting officer is required to obtain such clearance in writing. The contracting officer shall include the
following information in the preaward clearance request:
(1) Name, address, and telephone number of the prospective contractor and of any corporate
affiliate at which work is to be performed.
(2) Name, address, and telephone number of each proposed first-tier subcontractor with a
proposed subcontract estimated at million or more.
(3) Anticipated date of award.
(4) Information as to whether the contractor and first-tier subcontractors have previously held any
Government contracts or subcontracts.
(5) Place or places of performance of the prime contract and first-tier subcontracts estimated at
million or more, if known.
(6) The estimated dollar amount of the contract and each first-tier subcontract, if known.