EP 1110-1-8
(Vol. 9)
31 July 03
SECTION III: EFAR REFERENCE
EFARS PART 31
CONTRACT COST PRINCIPLE AND PROCEDURES
EAC 95-6
SUBPART 31.1 -- APPLICABILITY
31.105 Construction and Architect-Engineer Contracts.
(d)(2)(i)(b) In this case, equipment ownership and operating costs shall be
determined using the Construction Equipment Ownership and Operating Expense
Schedule published by the U.S. Army Corps of Engineers.
31.105-100 Contract Clause.
The contracting officer shall insert the statement at 52.231-5000 in all
solicitations and contracts for construction within the United States that are expected to
exceed the small purchase threshold.
EFARS Clause - 52.231-5000 Equipment Ownership and Operating Expense
Schedule.
As prescribed in 31.105-100, insert the following clause in all solicitations and
contracts for construction that are expected to exceed the small purchase threshold.
EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE (MAR
1995) EFARS.
(a) This clause does not apply to terminations. See 52.249-5000, Basis for
Settlement of Proposals, and FAR Part 49, Termination of Contracts.
(b) Allowable cost for construction and marine plant and equipment in sound
workable condition owned or controlled and furnished by a contractor or subcontractor
at any tier shall be based on actual cost data for each piece of equipment or groups of
similar serial and series for which the Government can determine both ownership and
operating costs from the contractor's accounting records. When both ownership and
operating costs cannot be determined for any piece of equipment or groups of similar
serial or series equipment from the contractor's accounting records, costs for that
equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction
Equipment Ownership and Operating Expense Schedule, Region [Insert roman numeral
for the appropriate region of the schedule]. Working conditions shall be considered to
ENGINEER FAR SUPPLEMENT
A-3