EP 1110-1-8
(Vol. 3)
31 July 03
Table 2-1. HOURLY EQUIPMENT OWNERSHIP AND OPERATING EXPENSE
VALUE
ADJUSTABLE
TOTAL HOURLY
REGION 3
FUEL TYPE
(TEV)
ELEMENTS
RATES ($/HR)
AVERAGE STANDBY DEPR
CAT
ID.NO.
MODEL
EQUIPMENT DESCRIPTION
2000 ($)
FCCM
FUEL
CWT
MAIN
CARRIER
C25
WACKER CORPORATION (continued)
C25WC003 CT46A
CONCRETE FINISHER, POWER TROWEL, 2 SETS
20 HP
G
,677
6.37
1.13
1.87
0.19
2.11
8
OF 4 - 48" DIA BLADES
SUBCATEGORY 0.20
VIBRATORY SCREED
ALLEN ENGINEERING CORP.
C25AJ003
12HED
CONCRETE, VIBRATORY SCREED, 12.5'
9 HP
G
,576
2.97
0.54
0.89
0.09
0.95
5
WIDE
C25AJ001
12 HD
CONCRETE, VIBRATORY SCREED, 20'
8 HP
G
,943
2.32
0.38
0.63
0.06
0.85
4
WIDE
C25AJ004
12HED
CONCRETE, VIBRATORY SCREED, 30'
9 HP
G
,966
3.72
0.77
1.27
0.13
0.95
8
WIDE
C25AJ005
12HED
CONCRETE, VIBRATORY SCREED, 40'
11 HP
G
,352
4.43
0.90
1.50
0.15
1.16
10
WIDE
C25AJ006
12HED
CONCRETE, VIBRATORY SCREED, 50'
11 HP
G
,106
4.98
1.07
1.78
0.18
1.16
12
WIDE
C25AJ007
12HED
CONCRETE, VIBRATORY SCREED, 55'
11 HP
G
,812
5.20
1.14
1.89
0.19
1.16
13
WIDE
SUBCATEGORY 0.25
VIBRATORY LASER SCREED
SOMERO ENTERPRISES, INC.
C25SV003 S-100
CONCRETE, VIBRATORY LASER SCREED, 8'
30 HP
D-off
7,734
24.96
8.17
11.96
2.19
1.33
72
WIDE X 12' BOOM
C25SV002 S-160
CONCRETE, VIBRATORY LASER SCREED, 8'
65 HP
D-off
7,946
42.18
13.56
19.86
3.63
2.87
126
WIDE X 20' BOOM
C25SV001 S-240
CONCRETE, VIBRATORY LASER SCREED, 12'
65 HP
D-off
3,643
51.55
16.87
24.70
4.52
2.87
151
WIDE X 20' BOOM
SUBCATEGORY 0.30
MATERIAL/TOPPING SPREADERS
ALLEN ENGINEERING CORP.
C25AJ008
SP23H
CONCRETE, MATERIAL/TOPPING SPREADER,
6 HP
G
,448
3.00
0.80
1.18
0.21
0.54
11
12.5' WIDE
C25AJ009
SP23H
CONCRETE, MATERIAL/TOPPING SPREADER,
6 HP
G
,278
3.14
0.86
1.25
0.23
0.54
12
20' WIDE
2-53