EP 1110-1-8
(Vol. 12)
31 July 03
Table 2-1. HOURLY EQUIPMENT OWNERSHIP AND OPERATING EXPENSE
VALUE
ADJUSTABLE
TOTAL HOURLY
REGION 12
FUEL TYPE
(TEV)
ELEMENTS
RATES ($/HR)
AVERAGE STANDBY DEPR
CAT
ID.NO.
MODEL
EQUIPMENT DESCRIPTION
2000 ($)
FCCM
FUEL
CWT
MAIN
CARRIER
C25
WACKER CORPORATION (continued)
C25WC003 CT46A
CONCRETE FINISHER, POWER TROWEL, 2 SETS
20 HP
G
,346
6.98
1.11
1.82
0.20
1.96
8
OF 4 - 48" DIA BLADES
SUBCATEGORY 0.20
VIBRATORY SCREED
ALLEN ENGINEERING CORP.
C25AJ003
12HED
CONCRETE, VIBRATORY SCREED, 12.5'
9 HP
G
,436
3.26
0.53
0.87
0.09
0.88
5
WIDE
C25AJ001
12 HD
CONCRETE, VIBRATORY SCREED, 20'
8 HP
G
,851
2.53
0.38
0.62
0.07
0.78
4
WIDE
C25AJ004
12HED
CONCRETE, VIBRATORY SCREED, 30'
9 HP
G
,779
4.13
0.76
1.24
0.14
0.88
8
WIDE
C25AJ005
12HED
CONCRETE, VIBRATORY SCREED, 40'
11 HP
G
,141
4.92
0.89
1.46
0.16
1.08
10
WIDE
C25AJ006
12HED
CONCRETE, VIBRATORY SCREED, 50'
11 HP
G
,858
5.57
1.06
1.74
0.19
1.08
12
WIDE
C25AJ007
12HED
CONCRETE, VIBRATORY SCREED, 55'
11 HP
G
,552
5.82
1.13
1.85
0.20
1.08
13
WIDE
SUBCATEGORY 0.25
VIBRATORY LASER SCREED
SOMERO ENTERPRISES, INC.
C25SV003 S-100
CONCRETE, VIBRATORY LASER SCREED, 8'
30 HP
D-off
3,487
28.14
8.12
11.59
2.32
1.25
72
WIDE X 12' BOOM
C25SV002 S-160
CONCRETE, VIBRATORY LASER SCREED, 8'
65 HP
D-off
1,022
47.49
13.47
19.25
3.84
2.70
126
WIDE X 20' BOOM
C25SV001 S-240
CONCRETE, VIBRATORY LASER SCREED, 12'
65 HP
D-off
4,939
58.12
16.75
23.94
4.78
2.70
151
WIDE X 20' BOOM
SUBCATEGORY 0.30
MATERIAL/TOPPING SPREADERS
ALLEN ENGINEERING CORP.
C25AJ008
SP23H
CONCRETE, MATERIAL/TOPPING SPREADER,
6 HP
G
,094
3.35
0.81
1.15
0.23
0.50
11
12.5' WIDE
C25AJ009
SP23H
CONCRETE, MATERIAL/TOPPING SPREADER,
6 HP
G
,907
3.51
0.85
1.22
0.24
0.50
12
20' WIDE
2-53