EP 1110-1-23
31 Jan 99
This scope of work will be incorporated as the last appendix in the draft air monitoring plan only.
Each page of the draft plan will be stamped "DRAFT." Submittals will include incorporation of
all previous Government review comments as well as the disposition of each comment.
Disposition of comments submitted with the final plan will be signed by the Designated IH and the
Monitoring Contractor. The information will be incorporated into the plan and included in all
subsequent air monitoring plan submittals.
4.2 Minutes of Meetings. Following each review conference, the Monitoring Contractor
will prepare and submit minutes of the meeting within 10 working days to the CO.
4.3 Correspondence. The Monitoring Contractor will keep a record of each phone
conversation and written correspondence where information related to the performance of this
contract is made. A summary of the phone conversation and written correspondence will be
submitted to the CO monthly. Points of contact for this contract are:
Installation POC (*)
U.S. Army Corps of Engineers, District, or CO (*)
4.4 Completion Dates.
Draft Air Monitoring Plans (*)
Final Air Monitoring Plans (*)
Draft Reports (*)
Final Reports (*)
Completion of Contract (*)
4.5 Addressees. Copies of plans and reports will be distributed to the following
addressees in the quantities indicated. (*)
A-9