EP 1110-1-19
30 Jun 01
professional/technical services to support construction of the remedial action. Institutional
controls, which are legal or administrative measures used to limit or restrict site access, can be a
major component of the RA (if required) and therefore warrant separate consideration.
Contingency is not included as a separate cost element since the costs reported in the RA report
are known, or actual, RA costs.
Exhibit 6-2
RA Capital and Operating Cost Elements
Cost Element
Description
Includes all preparatory work required during remedial action or construction. This
331XX.01
includes submittals; construction plans; mobilization of personnel, facilities and
equipment; construction of temporary facilities; temporary utilities; temporary
Preparatory Work
relocations and setup of decontamination facilities and construction plant.
Provides for all work during remedial action associated with air, water, sludge, solids
331XX.02
and soil sampling, monitoring, testing, and analysis. Includes sample taking, shipping
Monitoring,
samples and sample analysis by on-site and off-site laboratory facilities.
Sampling, Testing,
and Analysis
Sitework during remedial action consists of site preparation, site improvements, and
331XX.03
site utilities. Site preparation includes demolition, clearing, and earthwork. Site
Sitework
improvements include roads, parking, curbs, gutters, walks and other hardscaping.
Site utilities include water, sewer, gas, other utility distribution. Also includes new
fuel storage tanks. All work involving contaminated or hazardous material is excluded
from this system. Storm drainage involving contaminated surface water is included
under "Surface Water Collection and Control" (331XX.05). Note that topsoil, seeding,
landscaping and reestablishment of existing structures altered during remediation
activities are included in "Site Restoration" (331XX.20).
Includes the locating, removing, and destruction of all ordnance, conventional or
331XX.04
chemical, fused or unfused, related scrap, propellants, and delivery vehicles during
Ordnance and
remedial action. Providing for public involvement, providing subsurface data for the
Explosive-Chemical
delineating the extent of the contamination. Also includes the construction of
Warfare Material
temporary explosive storage bunkers and surveys.
Removal and
Destruction
Provides for the collection and control of contaminated surface water through the
331XX.05
construction of storm drainage piping and structures, erosion control measures, and
Surface Water
civil engineering structures such as berms, dikes and levees. Includes the collection of
Collection and
surface water through the construction of lagoons, basins, tanks, dikes, and pump
Control
systems. Includes transport to treatment plant.
Provides for the remedial action collection and control of contaminated groundwater
331XX.06
through the construction of piping, wells, trenches, slurry walls, sheet piling and other
Groundwater
physical barriers. Includes the collection of groundwater through the construction of
Collection and
lagoons, basins, tanks, dikes, and pump systems. Includes transport to treatment plant.
Control
Includes the remedial action construction for the collection and control of gas, vapor
331XX.07
and dust.
Collection and
Control
6-3