This guide is intended to assist in the preparation, review, or use of RA reports for
environmental restoration projects by cost engineers, environmental engineers, resident
construction managers, project managers, remedial project managers (RPMs), program
managers, and other related technical disciplines.
1-2. Applicability. This pamphlet applies to all USACE commands having investigation,
design, and remedial action responsibility for environmental restoration projects within the
military, civil works, or support for others programs.
1-3. Scope. This pamphlet is a companion document to A Guide for Preparing and
Reviewing Remedial Action Reports developed jointly by the U.S. Army Corps of Engineers
(USACE) and U.S. Environmental Protection Agency (USEPA). The primary difference
between these two documents is the cost reporting format. Both documents incorporate selected
guidance from the Guide to Documenting and Managing Cost and Performance Information for
Remediation Projects (EPA 542-B-98-007, October 1998). This guide does not address
construction completion, site completion, or site deletion from the National Priorities List (NPL).
For information on these issues refer to Close Out Procedures for National Priorities List Sites
(EPA 540-R-98-016, January 2000). Although much of this guide is written from the
perspective of a Superfund site listed on the NPL, the presented concepts could also be applied to
non-NPL sites or other cleanup programs.
1-4. References. The following documents provide additional information related to the
subject of this pamphlet.
a.
ER 5-1-11. Program and Project Management.
b.
ER 415-345-38. Transfer and Warranties.
c.
ER 1110-3-1301.
Hazardous, Toxic, and Radioactive Waste (HTRW) Cost
Engineering.
d.
CEGS 01070. Cost and Performance Report.
e.
CEGS 01440. Contractor Quality Control.
f.
CEGS 01450. Chemical Data Quality Control.
g.
Standard Industrial Classification Manual. 1987.
h.
40 CFR Part 300. National Oil and Hazardous Substances Pollution Contingency
i.
EPA 540-F-93-048.
Presumptive Remedies: Site Characterization and
Technology Selection for CERCLA Site with Volatile Organic Compounds in Soils. U.S.
Environmental Protection Agency. September 1993.
1-2