a planning period of less than six months, the lead agency must publish the Action Memorandum
within 60 days of initiating the removal action. Any information gathered during this response
action must be incorporated into the EE/CA document. The OE MCX should be contacted for
further information about the circumstances in which a removal action may be appropriate during
the OE response process.